Friday, July 30, 2010



Week two of framing and the house has begun to appear. Despite the 104 degree weather, the team of framers have been diligently working. The main living level has taken shape, the 16’ wide opening to the front deck, the opening to the rear terrace and screened porch have appeared. The cantilevers over the foundation are visible. Notice the pre-placed holes for the mechanical ductwork, that will supply air to the bedroom level. The site's topsoil still is tarped, to protect the soil from those sudden summer downpours we have in Georgia. We placed the project sign, that defines what makes a LEED home~ LEED. Next week the steel beams will be placed, so we should be closer to topping off the house.